Calculate the total operation time for this construction activity if the volume of soil to be removed is 8 cu.m. (considered 33% for bulking of materials.) The speed of dumptruck is 30 kph and travel distance (round trip) from the source to disposal area vice-versa is 6 km. The bucket size of excavator is 0.50 cu.m at 0.50 min loading time, tipping time is 4 mins.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 7RQ
icon
Related questions
Question

Calculate the total operation time for this construction activity if the volume of soil to be removed is 8 cu.m. (considered 33% for bulking of materials.) The speed of dumptruck is 30 kph and travel distance (round trip) from the source to disposal area vice-versa is 6 km. The bucket size of excavator is 0.50 cu.m at 0.50 min loading time, tipping time is 4 mins.

a. 15.18 minutes
b. 22.02 minutes
c. 25.32 minutes
d. 30.00 minutes
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Pricing excavation and backfill
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,