Draw an LSM schedule for a 5-mile stretch of a road project. Consider the following activities: Activity Daily production (LF) A. Excavation 500 B. Subbase 300 C. Base 240 D. Paving 1000 E. Stripping and signage 1500

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter10: Pricing Excavation And Backfill
Section: Chapter Questions
Problem 6RQ
icon
Related questions
Question
  1. Draw an LSM schedule for a 5-mile stretch of a road project. Consider the following activities:

Activity

Daily production (LF)

A. Excavation

500

B. Subbase

300

C. Base

240

D. Paving

1000

E. Stripping and signage

1500

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Measuring sitework, excavation and piling
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,