Jobs A, B, C, and D are in queue at work center 10 before being completed on work center 20. The table below pertains to the jobs and the work centers: (Job, Process time (day) at WC 10, process time (day) at WC 20, Due Date, arriving order). Today is day 1. Job Process Time Work Center Work Center 10 20 3 4 3 3 3 5 4 1 ABCI А с 2 1 4 3 If the jobs are scheduled by the shortest process time (SPT) rule, the total idle time (total of both WCs) during day 1 through day end (last job finishing date) is: Hint: you need to first determine the job's operation order by SPT rule. Then in each work center, you need to schedule each job's start date and end date on both WCs. 12 D 11 10 9 Due DateArriving order None of them 8 24 18 15

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
Jobs A, B, C, and D are in queue at work center 10 before being completed on work center 20. The table below pertains to
the jobs and the work centers: (Job, Process time (day) at WC 10, process time (day) at WC 20, Due Date, arriving order).
Today is day 1.
Job
Process Time
ABCD
Work Center Work Center
10
20
3
4
3
3
3
5
4
1
Due DateArriving
order
8
24
18
15
2143
D
If the jobs are scheduled by the shortest process time (SPT) rule, the total idle time (total of both WCs) during day 1
through day end (last job finishing date) is:
Hint: you need to first determine the job's operation order by SPT rule. Then in each work center, you need to schedule each
job's start date and end date on both WCs.
12
11
10
9
None of them
Transcribed Image Text:Jobs A, B, C, and D are in queue at work center 10 before being completed on work center 20. The table below pertains to the jobs and the work centers: (Job, Process time (day) at WC 10, process time (day) at WC 20, Due Date, arriving order). Today is day 1. Job Process Time ABCD Work Center Work Center 10 20 3 4 3 3 3 5 4 1 Due DateArriving order 8 24 18 15 2143 D If the jobs are scheduled by the shortest process time (SPT) rule, the total idle time (total of both WCs) during day 1 through day end (last job finishing date) is: Hint: you need to first determine the job's operation order by SPT rule. Then in each work center, you need to schedule each job's start date and end date on both WCs. 12 11 10 9 None of them
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,