Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: 2024 $ 2,550,000 5,950,000 2,050,000 1,825,000 2025 $4,250,000 1,700,000 4,750,000 4,100,000 Cost incurred during the year Estimated costs to complete as of year-end I Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. 2026 $1,870,000 Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. 0 3,200,000 4,075,000

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 10C
icon
Related questions
Question
Required information
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa
Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is
as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Revenue
Gross profit (loss)
2024
2024
2025
$ 2,550,000 $4,250,000
5,950,000
2,050,000
1,825,000
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.
2025
2026
1,700,000
4,750,000
4,100,000
2026
$1,870,000
8
3,200,000
4,075,000
Transcribed Image Text:Required information [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) 2024 2024 2025 $ 2,550,000 $4,250,000 5,950,000 2,050,000 1,825,000 Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. 2025 2026 1,700,000 4,750,000 4,100,000 2026 $1,870,000 8 3,200,000 4,075,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L