The following jobs are waiting to be processed at a small machine center: JOB DUE DATE 10 20 30 40 50 250 242 250 260 265 DURATION (DAYS) 20 10 16 34 6 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a) Sequence the jobs according to LPT. According to the LPT rule, the sequence of jobs should be

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The following jobs are waiting to be processed at a small machine center:
DUE DATE
250
242
250
260
265
JOB
10
20
30
40
50
DURATION (DAYS)
20
10
16
34
6
All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday)
in the order shown but are not scheduled to begin until day 201 (today).
a) Sequence the jobs according to LPT.
According to the LPT rulle, the sequence of jobs should be
b) What is the average completion (flow) time?
The average completion (flow) time is
c) What is the average job lateness?
The average job lateness is
d) What is the average number of jobs in the system?
The average number of jobs in the system is jobs (round your response to one decimal place).
days (round your response to one decimal place).
days (round your response to ane decimal place).
Transcribed Image Text:The following jobs are waiting to be processed at a small machine center: DUE DATE 250 242 250 260 265 JOB 10 20 30 40 50 DURATION (DAYS) 20 10 16 34 6 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 (yesterday) in the order shown but are not scheduled to begin until day 201 (today). a) Sequence the jobs according to LPT. According to the LPT rulle, the sequence of jobs should be b) What is the average completion (flow) time? The average completion (flow) time is c) What is the average job lateness? The average job lateness is d) What is the average number of jobs in the system? The average number of jobs in the system is jobs (round your response to one decimal place). days (round your response to one decimal place). days (round your response to ane decimal place).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.