Consider the PERT/CPM network with estimated times in weeks shown in the following figure. The project is scheduled to begin on May 1. Start Activity Variance A B с D E F G H The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity. 1.0 0.4 1.1 0.7 0.4 0.7 A 0.7 1.1 B 33 3 E D 2 F 2 3 H 7 Finish (a) Give the expected project completion date and the critical path. (Enter your critical path as a comma-separated list.) The expected project completion is weeks from May 1 with a critical path of (b) Based only on the critical path, by what date are you 99% sure the project will be completed? (Round your answer to one decimal place.) weeks from May 1.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
100%
You may need to use the appropriate technology to answer this question.
Consider the PERT/CPM network with estimated times in weeks shown in the following figure. The project is scheduled to begin on May 1.
Start
A
B
с
D
E
F
G
H
1.0
The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity.
Activity Variance
0.4
1.1
0.7
0.4
0.7
0.7
A
1
1.1
B
3
E
1
D
2
C
4
F
2
3
T
7
Finish
(a) Give the expected project completion date and the critical path. (Enter your critical path as a comma-separated list.)
The expected project completion is
weeks from May 1 with a critical path of
(b) Based only on the critical path, by what date are you 99% sure the project will be completed? (Round your answer to one decimal place.)
weeks from May 1.
Transcribed Image Text:You may need to use the appropriate technology to answer this question. Consider the PERT/CPM network with estimated times in weeks shown in the following figure. The project is scheduled to begin on May 1. Start A B с D E F G H 1.0 The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity. Activity Variance 0.4 1.1 0.7 0.4 0.7 0.7 A 1 1.1 B 3 E 1 D 2 C 4 F 2 3 T 7 Finish (a) Give the expected project completion date and the critical path. (Enter your critical path as a comma-separated list.) The expected project completion is weeks from May 1 with a critical path of (b) Based only on the critical path, by what date are you 99% sure the project will be completed? (Round your answer to one decimal place.) weeks from May 1.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.