Given the information provided below for Rockland, Inc., use the Total Supply Chain Cost Excel template in MindTap to compute the costs associated with the supply chain. The order quantity is Q = 11,000 units, and the supply chain operates 250 days per year. Annual Price per Demand (D) Unit (P) $7.85 Transport Cost per Unit (Ct) $4.70 132,000 Oversight Cost per Unit (O) One Year (Ch) Days (L) $0.25 $9.60 What if the supplier asks you to increase your order quantity to 22,000 units for a price discount of one percent, would you accept the new deal? Do not round intermediate calculations. Round your answers to the nearest dollar. 11,000 units 22,000 units Cost to Store Order Cost One Unit (Co) $160 Order Lead Time in $ $ $ $ 10 Order quantity: Total procurement cost: $ Total management oversight cost: $ Total annual transportation cost: $ Annual order cost: $ Annual holding cost: $ $ Average annual pipeline inventory cost: $ $ Total supply chain costs: $ $ If the supplier increases the order quantity to 22,000 units for a price discount of one percent, the total supply chain costs would -Select-increasedecreaseltem 15, so you should -Select-acceptrejectltem 16 the new deal.

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Chapter2: The Purchasing Process
Section: Chapter Questions
Problem 1GPE
icon
Related questions
Question
Given the information provided below for Rockland, Inc., use the Total Supply Chain Cost Excel template in MindTap to
compute the costs associated with the supply chain. The order quantity is Q = 11,000 units, and the supply chain
operates 250 days per year.
Transport
Cost per
Unit (Ct)
$4.70
Cost to Store
Order Cost One Unit
(Co)
$160
Order Lead
Time in
Annual Price per
Demand (D) Unit (P)
Oversight Cost
per Unit (O)
One Year (Ch) Days (L)
132,000
$7.85
$0.25
$9.60
10
What if the supplier asks you to increase your order quantity to 22,000 units for a price discount of one percent, would
you accept the new deal? Do not round intermediate calculations. Round your answers to the nearest dollar.
Order quantity:
11,000 units 22,000 units
Total procurement cost:
Total management oversight cost:
Total annual transportation cost:
Annual order cost:
$
$
$
$
$
$
$
$
Annual holding cost:
$
$
Average annual pipeline inventory cost: $
$
Total supply chain costs:
$
$
If the supplier increases the order quantity to 22,000 units for a price discount of one percent, the total supply chain costs
would -Select-increasedecreaseltem 15, so you should -Select-acceptrejectltem 16 the new deal.
Transcribed Image Text:Given the information provided below for Rockland, Inc., use the Total Supply Chain Cost Excel template in MindTap to compute the costs associated with the supply chain. The order quantity is Q = 11,000 units, and the supply chain operates 250 days per year. Transport Cost per Unit (Ct) $4.70 Cost to Store Order Cost One Unit (Co) $160 Order Lead Time in Annual Price per Demand (D) Unit (P) Oversight Cost per Unit (O) One Year (Ch) Days (L) 132,000 $7.85 $0.25 $9.60 10 What if the supplier asks you to increase your order quantity to 22,000 units for a price discount of one percent, would you accept the new deal? Do not round intermediate calculations. Round your answers to the nearest dollar. Order quantity: 11,000 units 22,000 units Total procurement cost: Total management oversight cost: Total annual transportation cost: Annual order cost: $ $ $ $ $ $ $ $ Annual holding cost: $ $ Average annual pipeline inventory cost: $ $ Total supply chain costs: $ $ If the supplier increases the order quantity to 22,000 units for a price discount of one percent, the total supply chain costs would -Select-increasedecreaseltem 15, so you should -Select-acceptrejectltem 16 the new deal.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning