Q1: In construction of a highway section, the earthwork information is available as shown in the table below. The free-haul distance is 500m and the swelling factor is 20%. Draw the mass haul diagram between station 3 + 00 and station 9 + 00 and determine the extra compensation that must be paid to the contractor when the overhaul price is $200/m3 station. Station Cut Fill 3 + 00 50 250 4 + 00 150 550 6 + 00 150 200 7+ 00 910 50 9 + 00

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter16: Budget Estimating
Section: Chapter Questions
Problem 4RQ: Prepare a typical bay estimate based on the following information: a. Bay size of 350 feet and a...
icon
Related questions
Question

 In construction of a highway section, the earthwork information is available as shown in the table below. The free-haul distance is 500m and the swelling factor is 20%. Draw the mass haul diagram between station 3 + 00 and station 9 + 00 and determine the extra compensation that must be paid to the contractor when the overhaul price is $200/m3 station.

Q1: In construction of a highway section, the earthwork information is available
as shown in the table below. The free-haul distance is 500m and the swelling
factor is 20%. Draw the mass haul diagram between station 3 + 00 and station 9
+ 00 and determine the extra compensation that must be paid to the contractor
when the overhaul price is $200/m3 station.
Station
Cut
Fill
3 + 00
50
250
4 + 00
150
550
6 + 00
150
200
7+ 00
910
50
9 + 00
Transcribed Image Text:Q1: In construction of a highway section, the earthwork information is available as shown in the table below. The free-haul distance is 500m and the swelling factor is 20%. Draw the mass haul diagram between station 3 + 00 and station 9 + 00 and determine the extra compensation that must be paid to the contractor when the overhaul price is $200/m3 station. Station Cut Fill 3 + 00 50 250 4 + 00 150 550 6 + 00 150 200 7+ 00 910 50 9 + 00
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Methods to determine productivity
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,